MARKET ACTIVITY

TSX +205.03 (0.80%) 25,897.48
TSX Venture +8.80 (1.34%) 667.45
ASX 200 +46.80 (0.56%) 8,344.30
S&P 500 +24.35 (0.41%) 5,916.93
BMO Junior Gold Index +2.18 (1.85%) 120.24
VanEck Jr Miners +1.33 (2.30%) 59.21
Sprott Junior Miners +1.01 (2.34%) 44.30

COMMODITY PRICES

Gold (US$/oz) -3.50 (0.11%) 3,223.10
Silver (US$/oz) -0.09 (0.28%) 32.59
Copper (US$/lb) -0.01 (0.16%) 4.68
Platinum (US$/oz) -4.70 (0.47%) 990.70
Palladium (US$/oz) -7.00 (0.72%) 960.00

MARKET MOVERS

 
Company Change Last Trade
Franco-Nevada 4.96 2.28 $222.04
Royal Gold 3.66 2.21 $169.29
Wheaton Precious Metals 3.09 2.89 $109.98
Agnico Eagle Mines 2.33 1.59 $148.70
Contango ORE 2.15 16.73 $15.00
Lundin Gold 1.22 2.21 $56.44
Newmont 1.18 2.42 $49.84
Torex Gold Resources 1.10 2.75 $41.15
Alamos Gold 1.02 3.07 $34.28
SSR Mining 0.94 6.56 $15.28
Perpetua Resources 0.90 5.59 $16.99
Altius Minerals 0.77 2.96 $26.82
Gold Fields 0.76 3.79 $20.79
China Gold Resources 0.74 8.69 $9.26
Eldorado Gold 0.71 2.92 $25.00

HIGH VOLUME

 
Company Volume Last Trade
Calibre Mining 5,991,910 $2.92
Global Tactical Metals 4,454,333 $0.02
Kinross Gold 3,123,336 $19.19
Baru Gold 3,101,123 $0.07
Alphamin Resources 3,027,995 $0.93
Capstone Copper 2,886,843 $6.83
OceanaGold 2,743,898 $5.67
B2Gold 2,517,367 $4.11
Talon Metals 2,138,029 $0.15
Discovery 2,035,499 $2.48
Ivanhoe Mines 1,975,913 $14.25
Equinox Gold 1,833,981 $8.43
Lundin Mining 1,817,321 $12.60
First Quantum Minerals 1,766,403 $20.09
Hudbay Minerals 1,740,101 $11.65

TORONTO, June 27, 2017 /CNW/ - New Gold Inc. ("New Gold") (TSX:NGD) (NYSE MKT:NGD) today provides an update on the construction of the company's Rainy River project, located in northwestern Ontario. Both the project schedule and capital cost estimate remain in line with New Gold's updated plan announced in late January 2017. The company continues to target first gold production in September 2017, and the estimated development capital cost from the beginning of this year to the targeted November 2017 commercial production remains $515 million.

Rainy River - Second Quarter 2017 Highlights

  • Project spending in the second quarter expected to be approximately $170 million, with estimated remaining capital to achieve November commercial production of approximately $220 million
  • The mining rate during the second quarter averaged approximately 115,000 tonnes per day despite impact of spring thaw
  • Public comment period for Schedule 2 amendment concluded on June 12th; amendment timeline accelerated to fourth quarter of 2017
  • Commissioning of primary crusher and conveyor system complete, with first crush completed on May 11, 2017 as planned
  • Installation of mechanical, piping, electrical and instrumentation in processing facilities over 95% complete
  • Ball and SAG mill achieved mechanical completion and hand over to operations for commissioning
  • Energization of all key site power lines completed on schedule
  • Overall earthworks over 85% complete

Figure 1. Rainy River open pit
New Gold 6 27 2017 1

Figure 2. Rainy River water management pond
New Gold 6 27 2017 2

Figure 3. Rainy River primary crusher and conveyor system successfully commissioned
New Gold 6 27 2017 3

Figure 4. Rainy River aerial view of process plant
New Gold 6 27 2017 4

Financial Update

  • Entered into gold price option contracts covering 120,000 ounces of second half 2017 production (20,000 ounces per month) ensuring a guaranteed floor price of $1,250 per ounce while providing continued exposure to increases in the gold price up to $1,400 per ounce
  • June 30, 2017 cash and cash equivalents expected to be approximately $175 million, with approximately $175 million also available under the revolving credit facility

"We are pleased with the solid progress we have made at Rainy River over the last five months," stated Hannes Portmann, President and Chief Executive Officer. "Through the second quarter, our team has both successfully commenced the staged commissioning of our process facility and delivered on our mining plan. As the pit has opened up, our operations team has recently delivered further increases in the mining rate, including several days over 130,000 tonnes per day."   

Overall earthworks are over 85% complete and are tracking in line with New Gold's updated plan. Starter cell rock deliveries are scheduled for completion in late August 2017. Energization of all key site overhead power lines and construction of the tailings pipeline corridor have been completed.     

All of the key structural components of the process facilities have been finalized and the setting of mechanical equipment and installation of piping, electrical and instrumentation services is close to completion. The primary crusher and conveyor system was successfully commissioned on schedule, and the first crush occurred on May 11, 2017. Commissioning of the ball mill and SAG mill has started and is scheduled to be completed in August 2017. The refining portion of the circuit should be ready to begin commissioning in July 2017. Dry and wet commissioning of the full process circuit is scheduled for August 2017.

The company requires an amendment to Schedule 2 of the Metal Mining Effluent Regulations to close two small creeks and deposit tailings. The proposed amendment was published in Canada Gazette I on May 13, 2017 and was followed by a 30-day public comment period which concluded on June 12, 2017. It is the company's understanding that the comments received during the comment period were all in support of the project proceeding as proposed. In light of the positive comments, the company has revisited the proposed timeline with Environment and Climate Change Canada and expects that adoption of the Schedule 2 amendment will be accelerated to the fourth quarter of 2017.  

As previously disclosed, New Gold is presently constructing a starter tailings cell, located within the broader tailings management area, that does not require a Schedule 2 amendment. This will allow New Gold to commence operations prior to completion of the Schedule 2 amendment. Based on its location and scale, the starter cell would provide capacity for approximately six months of production tailings when the mill is operating at full capacity.

In addition, New Gold has finalized the engineering design to construct the creek closures using sheet pile at the centre of the portion of the dam which will cover the creeks. The purpose of this approach is both to reduce the construction time after receipt of the Schedule 2 amendment, and most importantly, to be able to complete the work regardless of weather conditions. New Gold has met with the Ontario Ministry of Natural Resources and Forestry (MNRF) to review the design and has also filed its application for the required permit amendment in support of the design. It is expected that the Ontario MNRF will complete its review of the application during the third quarter of 2017.

Project spending at Rainy River during the second quarter is expected to be approximately $170 million, which would bring the total year-to-date project spending to approximately $295 million. The remaining capital cost to the targeted November commercial production is estimated to be approximately $220 million. Of the remaining expenditure, approximately 45% is related to mining and owner's costs, 45% is related to earthworks, including completion of the starter tailings cell, with the balance of the remaining expenditure related to the completion and commissioning of the process plant.

New Gold continues to look forward to the expected growth in the company's production and cash flow once Rainy River transitions into operation later this year. Rainy River has multiple important asset qualities including its great jurisdiction, significant annual production potential, long estimated reserve life and continued exploration potential.

Financial Update

Earlier this month, New Gold entered into gold price option contracts covering 120,000 ounces of its second half 2017 production (20,000 ounces per month). The company purchased put options at a strike price of $1,250 per ounce which were largely funded by selling call options at a strike price of $1,400 per ounce. The net cost to the company of the gold option contracts was less than $1 million. As announced on April 26, 2017, the company also fixed the price for 43.7 million pounds of the company's second half 2017 copper production at $2.73 per pound. These initiatives increase the company's cash flow certainty during the remaining Rainy River development period and through to its scheduled commercial production later this year.

About New Gold Inc.

New Gold is an intermediate gold mining company. The company has a portfolio of four producing assets and two significant development projects. The New Afton Mine in Canada, the Mesquite Mine in the United States, the Peak Mines in Australia and the Cerro San Pedro Mine in Mexico (which transitioned to residual leaching in 2016), provide the company with its current production base. In addition, New Gold owns 100% of the Rainy River and Blackwater projects located in Canada. New Gold's objective is to be the leading intermediate gold producer, focused on the environment and social responsibility. For further information on the company, please visit www.newgold.com.

Kenorland Minerals

Kenorland Minerals

Kenorland Minerals is focused on early to advanced stage exploration in North America. The Company holds a 4% net smelter return royalty on the Frotet Project in Quebec, owned by Sumitomo Metal Mining Canada Ltd. The Frotet Project hosts the Regnault gold system, a greenfields discovery made by Kenorland and Sumitomo Metal Mining Canada in 2020. Kenorland provides investors with exposure to over 1.5 million hectares of mineral rights being explored systematically... LEARN MORE

Newcore Gold

Newcore Gold

Newcore Gold is advancing the Enchi Gold Project in Ghana. The project’s 248 sq. km land package covers 40 kms of Ghana’s Bibiani Shear Zone, a gold belt which hosts several large, multi-million-ounce, gold deposits. A PEA completed in 2024 highlighted the robust economics of developing an open pit, heap leach mine at Enchi, with low capital intensity and strong leverage to the gold price. Enchi’s longer-term potential benefits from the district-scale exploration opportunity... LEARN MORE

Alaska Silver

Western Alaska Minerals

Alaska Silver is advancing its 100% owned, >49,000-acre Illinois Creek Mining District: Five high-grade deposits of gold, silver, copper, lead, and zinc at varying stages of exploration and deposit styles, including a silver-rich Carbonate Replacement Deposit (CRD) and an oxide gold deposit. Originally discovered in the 1980s (Anaconda Minerals), the Illinois Creek Mining District was consolidated by Alaska Silver’s management team over the past decade... LEARN MORE

Kodiak Copper

Kodiak Copper

Kodiak Copper is focused on discovering copper, the most critical metal for the energy transition and AI by exploring its projects in Canada and the USA. Kodiak's management team has shown the ability to raise capital while protecting a tight share structure and attracting strategic investors such as Teck Resources. The Company’s most advanced asset is the 100% owned MPD copper-gold porphyry project located in a producing mining district in the prolific Quesnel Trough... LEARN MORE

Freeport Resources

Freeport Resources

Freeport Resources is advancing one of the largest undeveloped copper deposits in the world. The 100% owned Yandera copper project covers approximately 245 square kilometers and is located in the highly prolific Papua New Guinea Orogenic Belt. Approximately $200 million in exploration and development expenditures have been spent on the project since 2005. The company has commenced work towards completing a Definitive Feasibility Study and has accelerated... LEARN MORE

Dryden Gold

Dryden Gold

Dryden Gold is an exploration company focused on the discovery of high-grade gold mineralization. The Company has a strong management team and Board of Directors comprised of experienced individuals with a track record of building shareholder value. Dryden Gold controls a 100% interest in a dominant strategic land position in the Dryden District of Northwestern Ontario. The property hosts high-grade gold mineralization over 50km of potential strike length along the... LEARN MORE

Core Nickel

Core Nickel

Core Nickel, junior exploration company, is advancing responsible exploration in Manitoba’s Thompson Nickel Belt. Focused on discovering high-grade magmatic nickel-sulphide deposits, Core Nickel’s key asset, the Mel deposit, holds a historic estimate of 5.3 million tonnes at 0.85% nickel. Positioned 25 km from the Thompson Mill, Mel benefits from nearby infrastructure. Core Nickel aims to increase responsibly sourced nickel supply for a net-zero, carbon-neutral future... LEARN MORE

South Pacific Metals

South Pacific Metals

South Pacific Metals is an emerging exploration company operating in Papua New Guinea’s proven gold and copper production corridors. With an expansive 3,000 km² land package and four transformative gold-copper projects contiguous with major producers K92 Mining, PanAust and neighbouring Barrick/Zijin, new leadership and experienced in-country teams are prioritizing thoughtful and rigorous technical programs focused on boots-on-the-ground exploration... LEARN MORE

Eagle Royalties

Eagle Royalties

Eagle Royalties holds a diverse portfolio of more than 35 royalty interests in western Canada. Target commodities subject to royalties include a broad spectrum including critical metals, precious metals, industrial minerals and diamonds. Its flagship royalty is associated with the AurMac Project located in Yukon, operated by Banyan Gold. The company also holds royalty interests on a number of historical base metal deposits located in Western Canada as well as... LEARN MORE

# DIAMOND STOCKS

  • Lucara Diamond (TSX: LUC)
  • Star Diamond (TSX: DIAM)
  • Mountain Province Diamonds (TSX: MPVD)
  • Diamcor Mining (TSX.V: DMI)
  • Arctic Star Exploration (TSX.V: ADD)

# GRAPHITE STOCKS

  • Nouveau Monde Graphite (TSX.V: NOU)
  • NextSource Materials (TSX: NEXT)
  • Graphite One (TSX.V: GPH)
  • Gratomic (TSX.V: GRAT)
  • Mason Graphite (TSX.V: LLG)

# NORDIC REGION STOCKS

  • District Metals (TSX.V: DMX)
  • Rupert Resources (TSX.V: RUP)
  • Mawson Gold (TSX: MAW)
  • Barsele Minerals (TSX.V: BME)
  • Aurion Resources (TSX.V: AU)