Dacian Gold Provides Update on Construction Activities at Mount Morgans Project

COMO, WA / November 16, 2017 / JMN Wire / Dacian Gold Ltd (ASX: DCN) is pleased to provide an updated photographic presentation of recent site construction activities at its 100%‐owned Mount Morgans Gold Project, located near Laverton in Western Australia.

Dacian Gold Executive Chairman Rohan Williams said the photos (contained in the accompanying presentation) clearly reflect the outstanding progress which had been achieved on numerous fronts at Mt Morgans since the last pictorial update in early September, including:

  • Construction of the 2.5Mtpa CIL treatment plant is now 70% complete, on schedule and on budget;
  • Underground mining at Beresford and now Allanson is 650m ahead of the corresponding Feasibility Study mining schedule;
  • Ore has been intersected on a second level at Beresford on the 2314 level, and a third level intersection of ore (2280 level) is expected by the end of the week;
  • Ore development on the 2297 level at Beresford has achieved 93m to date;
  • Construction of the Accommodation Village is complete, except for some minor works including final landscaping: all 400 rooms are operational;
  • Access tracks associated with installation of the 4km gas pipeline lateral has commenced;
  • Power station construction and hardware installation is progressing well;
  • Construction of the Jupiter Mine Service Area, including the administration complex, workshops and mines rescue/first aid centre has commenced;
  • Clearing of Heffernans Hill at Jupiter is complete and RC grade control drilling has commenced ahead of open pit mining scheduled to start next month;
  • Two underground grade control diamond drill rigs are continuing at Beresford, with strong results returned;
  • RC resource‐estimation drilling for oxide mineralisation at Cameron Well is underway; and
  • Three diamond drill rigs operating at Westralia are infill‐drilling the Inferred Mineral Resource to Indicated Mineral Resource, as well as commencing deeper resource‐extension drilling.

“Achieving these significant milestones six weeks out from the Christmas break is a remarkable achievement and a real credit to the construction, development and mining teams on site at Mount Morgans – all of whom are doing a fantastic job,” Mr Williams said.

“Construction of the new 2.5Mtpa CIL treatment plant is now well past the halfway point with the site currently a hive of activity and the very impressive structure shown in the attached photographs now well and truly taking shape,” he said.

“The construction program remains on time and on budget and we are confident we will achieve our target of pouring our first gold in March next year.

“At the same time, with first gold production now very much in sight we are continuing to aggressively pursue new growth of the Mount Morgans operation.

“We are increasing our resource‐focused drilling with four rigs now working around the clock at both Westralia and Cameron Well, in addition to a further three rigs undertaking grade control drilling at Beresford and Jupiter. And we have recently commenced reconnaissance aircore drilling at our next exploration target, called Basin Margin.”

Dacian Gold Ltd 11 16 2017

GET DAILY NEWS FLOW

Sign Up To Receive All Morning
News To Your Email Inbox

Please review our Disclaimer and Privacy Policy before subscribing.

Giga Metals

Giga Metals

Giga Metals is currently updating a Preliminary Economic Assessment (PEA) on its 100% owned Turnagain project. Turnagain is one of the largest undeveloped nickel-cobalt sulphide deposits in the world located in northern British Columbia. The project comes at an opportune time given growing demand in the EV industry for nickel and cobalt. The current NI 43-101 compliant resource contains 5.2 Blbs of nickel and 312 Mlbs of cobalt in the measured and indicated categories... LEARN MORE

No Internet Connection