Gascoyne Resources: Dalgaranga Construction Update - 3 Months to First Gold

West Perth, WA / February 15, 2018 / JMN Wire / Gascoyne Resources Limited (ASX: GCY) (“Gascoyne” or “Company”) is pleased to provide an update on construction activities at the Company’s Dalgaranga Gold Project, which contains a Measured, Indicated and Inferred Resource of 31.1Mt @ 1.3 g/t for 1,320,000 ounces of contained gold, which is inclusive of Proved and Probable Ore Reserves of 15.3Mt @ 1.3 g/t for 612,000 ounces of gold (see Figures 2 & 3 and Tables 1 & 2 below).

Highlights

  • Construction at Gascoyne’s Dalgaranga Gold Project is advancing well on all fronts and is currently within budget and approximately 1 month ahead of schedule.
  • Process plant construction is progressing on schedule for wet ore commissioning and first gold in May. Key activities include:
    • SAG Mill - Installation well advanced.
    • CIL tanks – completed.
    • Crusher - delivered to site and installation underway.
    • Ore Transfer Bin– construction completed.
    • Structural steel – fabrication complete and erection well advanced.
    • Elution Circuit– installation nearing completion.
    • Gold Room - construction nearing completion.
    • Installation of mechanical equipment – well advanced.
    • Electrical installation – underway.
  • Construction of the Dalgaranga airstrip – nearing completion.
  • Power Station and LNG storage tank installation – underway.
    • Generators are en route to Australia and on schedule for delivery to site in March.
    • LNG storage tank installation underway with first gas on schedule for mid-April
  • Mining Contractor mobilisation and site establishment – underway and on schedule to start mining in early March.

Gascoyne Resources Limited 2 15 2018

GET DAILY NEWS FLOW

Sign Up To Receive All Morning
News To Your Email Inbox

Please review our Disclaimer and Privacy Policy before subscribing.

ValOre Metals

ValOre Metals

ValOre Metals is a Canadian company with a portfolio of high‐quality exploration projects. The Company’s Pedra Branca PGE project in Brazil encompasses 38,940 hectares and consists of five distinct 2PGE+Au deposit areas that in aggregate host a N.I. 43-101 Inferred Resource of 1,067,000 ounces 2PGE+ Au contained in 27.2 million tonnes grading 1.22 g 2PGE+Au/t. PGE mineralization at Pedra Branca outcrops at surface and all currently known inferred resources... LEARN MORE